Current Activities
FLLAIR News
Gallery
Commission Updates
Phasing Plans
Current Activities


Construction Activities from April 14 - 19 and April 21 - 26  
Contractors will perform the following work:

Runway Structures (Areas 4 and 6)

  • Completing the installation of the mechanical, electrical, piping, and fire alarm systems in the utility building.  
  • Installing the ventilation, lighting, fire detection, and fire suppression systems in the tunnels. 

Ramps and Roadwork

  • Building the ramp and bridge structure in Area 1.
  • Preparing the site for the airport exit ramp to US 1 southbound.

 

Map of the work areas
Click on the image for a larger version.

Earthwork

  • Placing top soil and laying sod in Area 5.
  • Painting the retaining wall in Area 5.
  • Installing the fall protection system in Area 5.
  • Installing drainage in Areas 6, 9, and 10.
  • Trucks hauling fill to Areas 4, 6, 8, 9, and 10.
  • Building the retaining wall in Areas 4, 6, 8, 9, and 10.

Terminal 4 (Area 13)

  • Installing underground utilities.
  • Pouring the concrete pile caps, columns, and walls.
  • Constructing masonry walls.
  • Installing piles.
  • Installing shoring.
  • Placing structural beams
  • Installing the apron drainage.
  • Removing unsuitable materials for the apron 

Terminal 4 Parking Apron (Area 13)

  • Installing drainage.
  • Removing unsuitable materials. 

Runway Paving

  • Pouring the concrete base layer in Areas 10, 11, and 12.
  • Pouring the concrete top layer in Areas 10 and 11.
  • Installing utilities, signs, and lights in Areas 10, 11, and 12.
  • Paving the asphalt shoulders in Areas 10 and 11.
  • Preparing the ground for the shoulder asphalt paving in Areas 10 and 11.
  • Conducting site preparation in Areas 5, 6, 10, 11, and 12.
  • Installing FAA navigational equipment in Areas 5, 6, and 11. 

Terminal 3

  • Completing the terrazzo floor in the baggage claim level.
  • Installing the terrazzo floor near the pre-security shops and restaurants on the ticket counter level. 
     

Look at a larger version of the Construction Area Map (PDF).