​August

​Precast stairs are installed through the 5th floor
Meetings with the user groups regarding furniture continue

Aug. 25 Curtain wall system installation begins at the 2nd and 3rd floors
Aug. 21 Architectural precast panels are installed through the 5th floor
Aug. 19 10th Floor concrete slabs complete
​July

​Air handling units are delivered to the site
Review of audio visual bid documents begins

​July 30 ​Detention hollow metal door frames underway
July 25 6th Floor – 8th Floor concrete slabs complete
July 15

Meetings with the user groups regarding furniture begin
Review of the courtroom mockups begin

​June ​2nd floor rough-in of mechanical, plumbing, electrical and fire protection system begins
​June 25 ​6th floor concrete slab complete
​June 12 ​Contractor begins pouring the 6th floor concrete slab
​June 11 ​Installation of 22,000 gallon fuel tank for emergency generators
​June 4 ​5th floor concrete slab complete
​June 3 ​Installation of architectural precast panels begins on ground floor