• Photo is taken from the northwest showing the west façade of the courthouse building. Work is now happening on the 18th floor.
    Photo is taken from the northwest showing the west façade of the courthouse building. The 110 Tower is in the background.
  • Photo is taken from the southwest. The existing courthouse is in the foreground on Sixth Street.
    This is a southwest photo of the new tower with the Main Jail in the background. The existing courthouse is in the foreground on Sixth Street.
  • Work progresses on the entry lobby shown on the 2nd and 3rd floor. The main entry glass curtain wall is shown on the right.
    ​Work progresses on the entry lobby shown on the 2nd and 3rd floor. The main entry glass curtain wall is shown on the right.
  • Progress being made on the entry lobby shown from the  3rd floor includes interior partitions and duct work.
    ​Progress being made on the entry lobby shown from the 3rd floor includes interior partitions and duct work.
  • A view of the atrium east wall.
    A view of the atrium east wall. Work is underway constructing interior partitions, mechanical ducts, plumbing and more.
  • Ground floor escalator space/entry lobby space
    Ground floor escalator space/entry lobby space connection. The South Tower crane steel structure penetrating the building is shown on the right; escalator equipment is sitting on the floor.
  • This photo of the east façade
    This photo of the east façade includes the entry canopy steel structure (left), insulated glass panels on aluminum framing storefront system and south tower crane delivering materials (center). On the right, a Buck Hoist is stopped at the 15th floor showing main vertical support connected to each concrete slab.
  • Main elevator lobby at the 14th level
    Main elevator lobby at the 14th level. The elevator bank concrete wall is complete. All project concrete is pumped to all levels through the pipe shown on the center (future elevator lobby).
  • main entry interior
    Progress in work for the main entry interior includes partitions, mechanical ducts, electrical conduits and plumbing.
  • interior space
    Typical interior space showing mechanical ducts, cable trays and pipes for fire sprinklers.